State aid of over 77 million euros for Complexul Energetic Oltenia

State aid of over 77 million euros for Complexul Energetic Oltenia

The government is granting aid of over 77 million euros/386 million RON to the Oltenia Energy Complex, government spokesman Mihai Constantin announced on Friday. He said, at the end of the government meeting, that…




22:15, 18.01.2023

Gov't spokesperson: Currently, no question of dismissing any member of Cabinet following accident at Oltenia Energy Complex

The spokesperson of the Government, Dan Carbunaru, declared on Wednesday that, at this moment, there is no question of the resignation or dismissal of any member of the Cabinet, as a result of the tragic accident…




12:40, 18.01.2023

PM Ciuca asks for verifications on accident at Oltenia Energy Complex

Prime Minister Nicolae Ciuca requested the Energy minister to carry out verification regarding the causes leading to the accident which occurred at the Oltenia Energy Complex (CE), so that the fist conclusions…




09:00, 18.01.2023

Head of Oltenia Complex: Lorry involved in crash was meant for transporting goods not people

The general manager of the Oltenia Energy Complex (CE), Daniel Burlan, on Tuesday evening said that the lorry involved in the crash that took place at the Jilt Sud quarry was not approved for the transport of people,…




08:50, 18.01.2023

Jilt Sud Quarry work accident/EnergMin Popescu calls on three directors to resign

Energy Minister Virgil Popescu has asked three directors of the Oltenia Energy Complex who are directly responsible for the activity of the Jilt Sud Quarry to resign, saying that tragedies like the one on Tuesday,…




00:00, 18.01.2023

EnergMin visits Oltenia Energy Complex, on Tuesday evening

The Minister of Energy, Virgil Popescu, is going to the Oltenia Energy Complex on Tuesday evening, in the context of the accident resulting in the death of three people and the injury of 10 others that took place…




12:50, 14.10.2022

Alro gets selected by CE Oltenia to build electric plant on natural gas of 850 MW in Isalnita

The aluminum producer Alro has been selected, following an engaging selection process organized by the Oltenia Energy Complex, to jointly build the natural gas power plant at Isalnita, with a capacity of 850 MW,…




23:20, 08.03.2022

Prime Minister discusses with representatives of energy companies solutions to increase the level of energy independence

Prime Minister Nicolae Ciuca on Tuesday spoke with representatives of Romelectro, Hidroconstruct, Hidroelectrica, Oltenia Energy Complex and Hunedoara Energy Complex to identify solutions for developing the national…




16:00, 23.02.2022

New solar and gas power plants at Oltenia Energy Complex, hope for energy sector

The new projects being prepared by the Oltenia Energy Complex (CEO) represent the light at the end of the tunnel in the Romanian energy production sector, where nothing has been done for a long time, Sorin Elisei,…




13:55, 28.01.2022

Oltenia Energy Complex welcomes European Commission's decision to approve restructuring aid

The leadership of the Oltenia Energy Complex (CEO) welcomes the decision of the European Commission, announced on January 26, to approve the restructuring aid of up to 2.66 billion euros (13.15 billion RON) ensuring…




21:55, 26.01.2022

European Commission approves restructuring aid of up to 2.7 billion euros for Oltenia Energy Complex

The European Commission (EC) has approved, in accordance with EU state aid rules, Romania's plans to provide a restructuring aid worth up to 2.66 billion euros (13.15 billion lei) to Oltenia Energy Complex, announces…




16:20, 17.11.2021

Oltenia Energy Complex expects restructuring plan to be approved by European Commission in January 2022

The European Commission could approve the restructuring plan of the Oltenia Energy Complex in January 2022, after the company proves that there are investors interested in its development projects, the chairman…




19:00, 15.04.2021

RON 664.1 million in gov't endorsed state aid for Oltenia Energy Compex

The government adopted on Thursday an emergency ordinance on the granting of state aid of 664.1 million lei to the Oltenia Energy Complex (CEO), for the purchase of emission certificates for last year, according…




18:25, 15.04.2021

PM Citu announces adoption of emergency ordinance on Oltenia Energy Complex restructuring plan

The government adopted at its meeting this Thursday an emergency ordinance on the restructuring plan of the Oltenia Energy Complex, a plan that has already been greenlighted by the European Commission, and which…




09:07, 13.04.2020

CE Oltenia employees to be put on furlough, by rotation, as of 13 April and until 17 June

The approximately 13,000 employees of the Compex Energetic Oltenia - CEO (Oltenia Energy Complex) will be put on furlough, by rotation, as of 13 April and until 17 June, the measure being taken as a result of the…




23:28, 18.02.2020

Head of competition watchdog: Talks with EC underway over state aid to Oltenia Energy Complex, Tarom

Talks are underway between the Romanian authorities and the European Commission regarding the grant of state aid to the Oltenia Energy Complex - affected by the increase in the price of greenhouse gas emission…




23:00, 05.02.2020

Gov't approves 1.2 bln lei worth of state aid for Oltenia Energy Complex

The government approved on Tuesday the Emergency Ordinance under which the Oltenia Energy Complex receives 1.2 billion lei in state aid for the purchase of the greenhouse gas emission certificates assigned to 2019,…




12:48, 28.01.2020

Economy Minister: Head of Oltenia Energy Complex, Sorin Boza, dismissed due to prejudice brought to company

The Supervisory Board of the Oltenia Energy Complex decided to replace the director general of the company, Sorin Boza, due to the prejudice brought to the company and the fact that he was selected illegally, the…




19:46, 01.10.2019

Oltenia Energy Complex: Romania may request EU money to replace coal, same as Germany, Poland

Romania has to make a cost assessment of coal replacement for energy production and for industrial and professional conversion in Gorj and Jiu Valley and to request in Brussels European funds to make this transition,…




14:54, 19.12.2016

13 Oltenia Energy Complex employees on hunger strike

A number of 13 employees with the Oltenia Energy Complex, trade union members, went on hunger strike on Monday morning, protesting the fact that the company's revised revenue and expense budget for this year hasn't…